- Oct 24, 2023
- 17
- 12
- Funster No
- 99,487
- MH
- Carado i338
- Exp
- Caravan since 2014, Motorhome 2025
I have a Carado, existing 12V setup is as per this diagram, all under the front seats (apart from the fridge!)
I've measured the WA121545 and its a bit disappointing, I get 40A, which is only 20A into the battery with the fridge running. so , I may replace the WA121545 with an orion XS.
I've also been looking at the EBL31 and am beginning to not see the point of it. I'm not using its mains charger as it doesn't do lithium properly (AC side not in the above drawing but I have a Victron Bluesmart in place at the moment, this may change). Its not doing the fridge relay or the B2B relay in my vehicle, its not doing solar, and there are too few outputs that are on the "always on" side of the panel master switch (e.g. the fridge and the b2b relay are on the switched side) for my needs. so it may be simpler just to replace it with a simple 12v distribution board and I gain some space.
I intend to add a 24V battery and inverter to serve AC loads, together with solar and B2B charging. 12V loads will still be served from the existing 12V battery. The changes I intend to make are as below.
12V:
24V
add a complete 24V system (a little further back in the vehicle, but not in the garage, due to weight). I don't wish to add inverter/solar etc to the 12v , and wish to use 24v for the reasons of cable + fuse sizing, inverter size and efficiency, solar sizing, etc.
questions / debate:
1. the chassis ground point as is , comes from on the starter battery -ve . Do I need to take the -ve of my 2nd -ve bus bar serving the 24v kit to the starter battery -ve, or the 1st busbar? Does it need to be in 50mm ? Do I need to increase cable size all the way back to the starter?
I think yes because of the flow between 24v battery and inverter can in worst case situation go this way, but appreciate a sanity check, if the work is needed or not.
2. The 12-24V B2B: at this time I will not be able to run both this and 12-12 B2B in parallel as I have not enough on the alternator side (its configured for 50A, both cabling and fuses from battery to alternator). Debating whether to wire B2B's in parallel and use remote on/off switches so as to only ever run one at once, or to wire effectively in series i.e. connect the 12-24 B2B to the leisure side of the 12-12 b2b. thus using the 12v leisure as a buffer and guaranteeing never to overload the alternator side. Use GX and BMV monitoring SOC to decide when to switch 12-24 B2B on or not. If I do this it changes where the "vehicle side" supply to the 12-24V b2b comes from of course.
ta for any help
Ian
I've measured the WA121545 and its a bit disappointing, I get 40A, which is only 20A into the battery with the fridge running. so , I may replace the WA121545 with an orion XS.
I've also been looking at the EBL31 and am beginning to not see the point of it. I'm not using its mains charger as it doesn't do lithium properly (AC side not in the above drawing but I have a Victron Bluesmart in place at the moment, this may change). Its not doing the fridge relay or the B2B relay in my vehicle, its not doing solar, and there are too few outputs that are on the "always on" side of the panel master switch (e.g. the fridge and the b2b relay are on the switched side) for my needs. so it may be simpler just to replace it with a simple 12v distribution board and I gain some space.
I intend to add a 24V battery and inverter to serve AC loads, together with solar and B2B charging. 12V loads will still be served from the existing 12V battery. The changes I intend to make are as below.
12V:
- change the fuse on the 12v lithium leisure from 50A blade inline to 50A MRBF on the terminal for improved safety
- Add shunt so it can be measured
- orion XS 12-12 to replace the WA, so I have better efficiency and proper control
- add a simple DC distributor in parallel to the EBL, then debate whether to remove EBL or not...
24V
add a complete 24V system (a little further back in the vehicle, but not in the garage, due to weight). I don't wish to add inverter/solar etc to the 12v , and wish to use 24v for the reasons of cable + fuse sizing, inverter size and efficiency, solar sizing, etc.
questions / debate:
1. the chassis ground point as is , comes from on the starter battery -ve . Do I need to take the -ve of my 2nd -ve bus bar serving the 24v kit to the starter battery -ve, or the 1st busbar? Does it need to be in 50mm ? Do I need to increase cable size all the way back to the starter?
I think yes because of the flow between 24v battery and inverter can in worst case situation go this way, but appreciate a sanity check, if the work is needed or not.
2. The 12-24V B2B: at this time I will not be able to run both this and 12-12 B2B in parallel as I have not enough on the alternator side (its configured for 50A, both cabling and fuses from battery to alternator). Debating whether to wire B2B's in parallel and use remote on/off switches so as to only ever run one at once, or to wire effectively in series i.e. connect the 12-24 B2B to the leisure side of the 12-12 b2b. thus using the 12v leisure as a buffer and guaranteeing never to overload the alternator side. Use GX and BMV monitoring SOC to decide when to switch 12-24 B2B on or not. If I do this it changes where the "vehicle side" supply to the 12-24V b2b comes from of course.
ta for any help
Ian